[单选题]

Should a company accept a project that has an IRR of 14% and an NPV of $2.8 million if the cost of capital is 12%?

A.Yes,based only on the NPV.

B.Yes,based on the NPV and the IRR.

C.No,based on both the NPV and IRR.