[单选题]
In a project plan,when the project manager schedulesactivities,he (or she) often uses ( ) method,precedence relationships between activities are represented bycircles connected by one or more arrows.The length of the arrow represents theduration of therelevant activity.
A.causality diagram
B.Gantt chart
C.histogram
D.arrow diagram