[单选题]

In a project plan,when the project manager schedulesactivities,he (or she) often uses ( ) method,precedence relationships between activities are represented bycircles connected by one or more arrows.The length of the arrow represents theduration of therelevant activity.

A.causality diagram

B.Gantt chart

C.histogram

D.arrow diagram

参考答案与解析: