[单选题]

( ) is a method used in Critical Path Methodology for constructing aproject schedulenetwork diagram that uses boxes or rectangles, referred to as nodes, torepresent activities andconnects them with arrows that show the logical relationships that existbetween them.

A.PERT

B.AOA

C.WBS

D.PDM

参考答案与解析: