associated with its petrol-driven ferries and have made a strategic decision to dispose of these. They are now
considering entering into a contract with the Newman Steamship Company (NSC), a shipping organisation based
in Robynland. The contract would entail NSC providing transport to and from Cinola Island for all visitors to the
zoo and circus.
A.s a result of negotiations with NSC, the directors of Wonderland plc are considering two options whereby NSC
will become responsible for the transportation of visitors to and from Cinola Island with effect from 1 December
2007 or 1 December 2008.
A.dditional information is available as follows:(1) NSC would require Wonderland plc to pay for the necessary modifications to their steamships in order that
they would satisfy marine regulations with regard to passenger transportation. The only firm which could
undertake this work is currently working to full capacity and would require a payment of £2,450,000 in
order to undertake the work necessary so that the ferries could be in operation by 1 December 2007. The
same firm would require a payment of £1,725,000 in order to make the necessary modifications so that
the ferries could be in operation by 1 December 2008. The government of Robynland would be willing to
pay a grant of 8% towards the cost of getting the ferries into operation by 1 December 2007, but would not
be willing to pay a grant in respect of any later date.(2) On 1 December 2002 Wonderland plc paid £500,000 to the Port Licencing Authority of Robynland. This
payment was for a licence which entitles Wonderland plc to use all harbour facilities in Robynland during
the five-year period ending 30 November 2007. The licence could be renewed on 1 December 2007 at a
cost of £150,000 per annum.(3) Redundancy payments would need to be paid in respect of loss of employment. These would amount to
£1,200,000 if the contract with NSC commenced on 1 December 2007. This amount would reduce to
£750,000 if the contract commenced on 1 December 2008.(4) Wonderland plc has a contract for the provision of petrol for its ferries which is due to expire on 30 November
2008. Early termination of the contract would incur a penalty charge of £76,000. An emergency reserve
stock of petrol held by Wonderland plc, which cannot be used after 30 November 2007 due to marine
regulations regarding the age of fuel, could be sold for £55,000 on 1 December 2007 but not on any date
thereafter.(5) The ferries could be sold for £3,300,000 on 1 December 2007. If retained after 1 December 2007 the
ferries would require servicing during the year ending 30 November 2008 which would incur costs
amounting to £150,000. The resale value of the ferries on 1 December 2008 would be £2,900,000.(6) Stock of consumable items which originally cost £150,000 could be sold on 1 December 2007 for
£110,000 and on 1 December 2008 for £50,000.
Required:(i) On purely financial grounds, advise whether the management of Wonderland plc should enter into a
contract with NSC with effect from 1 December 2007 or 1 December 2008. You may ignore the time
value of money. (9 marks)
[试题](d) Explain to the management of Bailey’s why consideration should be given to resolving the problems through:(i) job rotation; (5 marks)
[多选题] PLC扩展单元有()和A/D、D/A转换等模块。A .输出B .输入C .高速计数D .转矩转电压E .转速转频率
[单选题]Human resource management is the management of humanresources.It is functio
[单选题]The quality management plan should describe how the project management team
They need more specific management regulations, and in more details as well. The
[单选题] Configuration management is the process of managing change in hardware, software, firmware, documentation, measurements, etc. As change requires an initial state and next state, the marking of significant states within a series of several changes be
[单选题]Project()Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval,and ultimate disposition of project information.() A.Integration B.Time C.Planning
[单选题]C.onfiguration management is the process of managing change in hardware,software,firmware,documentation,measurements,etc.As change requires an initial state and next state,the marking of significant states within a series of several changes becomes i
[单选题]( )is a project management technique for measuring project performance and progress.It has the ability to combine measurements of the project management triangle: scope , time and costs.A.Critical path method(CPM)B.Earned value management(EVM)C.Net p
[试题] A project management technique that is currently in widespread use is the (71) . The purpose of this technique is to detail, in hierarchical fashion, all of the activities that are required to meet project objectives. There are some special activitie